Is it permissible to withhold the remaining dues of a worker (plasterer and painter) due to his poor workmanship and delayed completion, especially when there are defects that require rectification at the original employer's expense?

Share this answer

Source: FtawySummarized from the full answer at Ftawy · imported Sep 2, 20261 min readAlso available in العربية
The answer

You have the right to deduct from the worker's wage an amount equivalent to compensation for defects in his work. It is permissible to deduct the wage of a worker who was late in completing the work or did not complete it as agreed. The deduction should be commensurate with the compensation for defects and the damage resulting from the delay. Experts should be consulted in assessing these matters.

Summarized from the full answer at Ftawy · imported

Read the full answer on Ftawy
Source platform
Ftawy
Original fatwa ID
180665
Imported
Translation status
Source text, unreviewed
Read the full ruling
Read the full answer on Ftawy